Project Name:
Project Start Time:
2024-09-19 10:26
Construction Progress:
Grind off old plates,derusting the drum surface use special tools.
Grind off old plates,derusting the drum surface use special tools.
Installing SS plates & welding.
Installing SS plates & welding.
Grinding all above & Photos after completion
Grinding all above & Photos after completion
Job Done
Job Done
Project Name:
Project Start Time:
2024-09-14 11:47
Construction Progress:
Upper platform condition : Need to remove the upper platform including pin
Upper platform condition : Need to remove the upper platform including pin
Davit/Winch deformed : Foundation eyes *2pcs & Long shaft * 1pc needed to fabricate . The davit moved from original position needed to be rectified
Davit/Winch deformed : Foundation eyes *2pcs & Long shaft * 1pc needed to fabricate . The davit moved from original position needed to be rectified
New ladder installing plan :Sample as another vessel
New ladder installing plan :Sample as another vessel
Job done
Job done
Project Start Time:
2024-09-13 15:44
Construction Progress:
No.4 ,No.3 &No.2 Scrubber damper repair work
No.4 ,No.3 &No.2 Scrubber damper repair work
Removal of Valves & Disassemble at workshop
Removal of Valves & Disassemble at workshop
Recondition/repair/Assembling/testing at work shop
Recondition/repair/Assembling/testing at work shop
Job done
Job done
Project Name:
Project Start Time:
2024-09-10 15:18
Construction Progress:
Check and set up scaffolding, cut through broken cell guides.
Check and set up scaffolding, cut through broken cell guides.
Fixing, welding and grinding of new cell guides and enter guide
Fixing, welding and grinding of new cell guides and enter guide
New cell guides paint.
New cell guides paint.
Job done
Job done
Project Start Time:
2024-08-19 15:53
Construction Progress:
Scrubber repair Background
Scrubber repair Background
Welding the plates
Welding the plates
Back check no welding penetration & Grinding smooth
Back check no welding penetration & Grinding smooth
PT checking after welding.
PT checking after welding.
Project Name:
Project Start Time:
2024-08-17 15:28
Construction Progress:
Check and dismantle Main engine rocker arm bolts and accessory.
Check and dismantle Main engine rocker arm bolts and accessory.
Start turning and measure rocker arm clearance
Start turning and measure rocker arm clearance
Reassemble accessories and bolts and the rocker arm operates normally after the test, and the inspection result is normal.
Reassemble accessories and bolts and the rocker arm operates normally after the test, and the inspection result is normal.
Job done
Job done
Project Name:
Project Start Time:
2024-08-13 15:19
Construction Progress:
Scrubber smoke pipe repair
Scrubber smoke pipe repair
weld and polish
weld and polish
Additional Installation cable trunk safety edge
Additional Installation cable trunk safety edge
Making a new safety edge ,put up a fireproof cloth and weld the cable trunk safety edge.
Making a new safety edge ,put up a fireproof cloth and weld the cable trunk safety edge.
Project Name:
Project Start Time:
2024-08-10 08:17
Construction Progress:
Cleaning & Inspection
Cleaning & Inspection
Grinding & Thickness measurement
Grinding & Thickness measurement
Welding & Grinding smooth
Welding & Grinding smooth
PT checking after welding
PT checking after welding
Project Name:
Project Start Time:
2024-08-04 11:42
Construction Progress:
Fabricated hoisting frame and special tools with I-bars Remove/assemble drum from windlass body
Fabricated hoisting frame and special tools with I-bars Remove/assemble drum from windlass body
Take measurements for shaft and bush hole, found the bush hole was out-of-round urgent arranged chain drum to workshop for boring
Take measurements for shaft and bush hole, found the bush hole was out-of-round urgent arranged chain drum to workshop for boring
PT for chain drum and Anchor test
PT for chain drum and Anchor test
Job done
Job done
Project Name:
Project Start Time:
2024-08-01 15:54
Construction Progress:
Pre-construction inspection & Measuring and scribing the cutting width
Pre-construction inspection & Measuring and scribing the cutting width
cutting after Reinforced welded lifting eye
cutting after Reinforced welded lifting eye
Weld and polish the ventilation tower
Weld and polish the ventilation tower
Check the whole after finished
Check the whole after finished
Project Name:
Project Start Time:
2024-07-29 15:41
Construction Progress:
D/G 1 Overhaul Process
D/G 1 Overhaul Process
Decommission No.1 D/G, dismantle components including the cylinder cover, piston, and connecting rod, and remove associated pipes.
Decommission No.1 D/G, dismantle components including the cylinder cover, piston, and connecting rod, and remove associated pipes.
Overhaul the engine by replacing the crankshaft, bearings, piston rings, and other worn parts
Overhaul the engine by replacing the crankshaft, bearings, piston rings, and other worn parts
Reassemble the engine, conduct pressure tests, and perform operational tests to ensure functionality and safety.
Reassemble the engine, conduct pressure tests, and perform operational tests to ensure functionality and safety.
Project Start Time:
2024-07-21 15:38
Construction Progress:
l NO 13 MANUAL CALL POINT WAS BURNT
l NO 13 MANUAL CALL POINT WAS BURNT
Before replace encode new point and New smoke sensor replaced
Before replace encode new point and New smoke sensor replaced
System checking that main board was burnt then New main eboard rplaced
System checking that main board was burnt then New main eboard rplaced
Job done
New main board replaced and testing normally