Project Start Time:

2024-09-19 10:26


Construction Progress:

Grind off old plates,derusting the drum surface use special tools.

Grind off old plates,derusting the drum surface use special tools.

Installing SS plates & welding.

Installing SS plates & welding.

Grinding all above & Photos after completion

Grinding all above & Photos after completion

Job Done

Job Done

Project Start Time:

2024-09-14 11:47


Construction Progress:

Upper platform condition : Need to remove the upper platform including pin

Upper platform condition : Need to remove the upper platform including pin

Davit/Winch deformed : Foundation eyes *2pcs & Long shaft * 1pc needed to fabricate . The davit moved from original position needed to be rectified

Davit/Winch deformed : Foundation eyes *2pcs & Long shaft * 1pc needed to fabricate . The davit moved from original position needed to be rectified

New ladder installing plan :Sample as another vessel

New ladder installing plan :Sample as another vessel

Job done

Job done

Project Start Time:

2024-09-13 15:44


Construction Progress:

No.4 ,No.3 &No.2 Scrubber damper repair work

No.4 ,No.3 &No.2 Scrubber damper repair work

Removal of Valves & Disassemble at workshop

Removal of Valves & Disassemble at workshop

Recondition/repair/Assembling/testing at work shop

Recondition/repair/Assembling/testing at work shop

Job done

Job done

Project Start Time:

2024-09-10 15:18


Construction Progress:

Check and set up scaffolding, cut through broken cell guides.

Check and set up scaffolding, cut through broken cell guides.

Fixing, welding and grinding of new cell guides and enter guide

Fixing, welding and grinding of new cell guides and enter guide

New cell guides paint.

New cell guides paint.

Job done

Job done

Project Start Time:

2024-08-19 15:53


Construction Progress:

Scrubber repair Background

Scrubber repair Background

Welding the plates

Welding the plates

Back check no welding penetration & Grinding smooth

Back check no welding penetration & Grinding smooth

PT checking after welding.

PT checking after welding.

Project Start Time:

2024-08-17 15:28


Construction Progress:

Check and dismantle Main engine rocker arm bolts and accessory.

Check and dismantle Main engine rocker arm bolts and accessory.

Start turning and measure rocker arm clearance

Start turning and measure rocker arm clearance

Reassemble accessories and bolts and the rocker arm operates normally after the test, and the inspection result is normal.

Reassemble accessories and bolts and the rocker arm operates normally after the test, and the inspection result is normal.

Job done

Job done

Project Start Time:

2024-08-13 15:19


Construction Progress:

Scrubber smoke pipe repair

Scrubber smoke pipe repair

weld and polish

weld and polish

Additional Installation cable trunk safety edge

Additional Installation cable trunk safety edge

Making a new safety edge ,put up a fireproof cloth and weld the cable trunk safety edge.

Making a new safety edge ,put up a fireproof cloth and weld the cable trunk safety edge.

Project Start Time:

2024-08-10 08:17


Construction Progress:

Cleaning & Inspection

Cleaning & Inspection

Grinding & Thickness measurement

Grinding & Thickness measurement

Welding & Grinding smooth

Welding & Grinding smooth

PT checking after welding

PT checking after welding

Project Start Time:

2024-08-04 11:42


Construction Progress:

Fabricated hoisting frame and special tools with I-bars Remove/assemble drum from windlass body

Fabricated hoisting frame and special tools with I-bars Remove/assemble drum from windlass body

Take measurements for shaft and bush hole, found the bush hole was out-of-round urgent arranged chain drum to workshop for boring

Take measurements for shaft and bush hole, found the bush hole was out-of-round urgent arranged chain drum to workshop for boring

PT for chain drum and Anchor test

PT for chain drum and Anchor test

Job done

Job done

Project Start Time:

2024-08-01 15:54


Construction Progress:

Pre-construction inspection & Measuring and scribing the cutting width

Pre-construction inspection & Measuring and scribing the cutting width

cutting after Reinforced welded lifting eye

cutting after Reinforced welded lifting eye

Weld and polish the ventilation tower

Weld and polish the ventilation tower

Check the whole after finished

Check the whole after finished

Project Start Time:

2024-07-29 15:41


Construction Progress:

D/G 1 Overhaul Process

D/G 1 Overhaul Process

Decommission No.1 D/G, dismantle components including the cylinder cover, piston, and connecting rod, and remove associated pipes.

Decommission No.1 D/G, dismantle components including the cylinder cover, piston, and connecting rod, and remove associated pipes.

Overhaul the engine by replacing the crankshaft, bearings, piston rings, and other worn parts

Overhaul the engine by replacing the crankshaft, bearings, piston rings, and other worn parts

Reassemble the engine, conduct pressure tests, and perform operational tests to ensure functionality and safety.

Reassemble the engine, conduct pressure tests, and perform operational tests to ensure functionality and safety.

Project Start Time:

2024-07-21 15:38


Construction Progress:

l NO 13 MANUAL CALL POINT WAS BURNT

l NO 13 MANUAL CALL POINT WAS BURNT

Before replace encode new point and New smoke sensor replaced

Before replace encode new point and New smoke sensor replaced

System checking that main board was burnt then New main eboard rplaced

System checking that main board was burnt then New main eboard rplaced

Job done

New main board replaced and testing normally