Project Start Time:

2026-09-09 17:08


Construction Progress:

Renew floor brackets and weld stiffeners in FPT

Renew floor brackets and weld stiffeners in FPT

Reinforcement installation below deck for crosshead lube oil pump

Reinforcement installation below deck for crosshead lube oil pump

Tighten flange bolts of expansion joint at the top of scrubber

Tighten flange bolts of expansion joint at the top of scrubber

The spare main engine piston, after being placed on the piston tool platform, interferes with the pipelines and supports below

The spare main engine piston, after being placed on the piston tool platform, interferes with the pipelines and supports below

Project Start Time:

2026-09-04 11:24


Construction Progress:

Details Of Service

Details Of Service

Underwater diver plugging operation

Underwater diver plugging operation

Replacement of the valve was done by crew

Replacement of the valve was done by crew

Supply of the new valve

Supply of the new valve

Project Start Time:

2026-09-02 14:51


Construction Progress:

Details Of Service

Details Of Service

Secure crosshead & Remove worn old crosshead lower bearing

Secure crosshead & Remove worn old crosshead lower bearing

New bearing installation & Hydraulic bolt tightening work

New bearing installation & Hydraulic bolt tightening work

job done

job done

Project Start Time:

2026-09-01 15:47


Construction Progress:

Details Of Service

Details Of Service

Preparatory Operations

Preparatory Operations

Crack Treatment

Crack Treatment

Welding Repair & Inspection

Welding Repair & Inspection

Project Start Time:

2026-05-12 09:05


Construction Progress:

Site Preparation & Material/Structure Positioning

Site Preparation & Material/Structure Positioning

Component Pre-Fit & Temporary Fixing

Component Pre-Fit & Temporary Fixing

Formal Full Welding Operation & Post-Weld Treatment

Formal Full Welding Operation & Post-Weld Treatment

Final Inspection & Work Completion

Final Inspection & Work Completion

Project Start Time:

2026-05-08 08:36


Construction Progress:

Preparation & Dismantle Old Bolts

Preparation & Dismantle Old Bolts

Install New Bolts

Install New Bolts

Final Verification

Final Verification

Project Start Time:

2026-04-20 15:12


Construction Progress:

Preparation & Dismantling

Preparation & Dismantling

Old Bellows Removal

Old Bellows Removal

Apply Sealant

Apply Sealant

Jobs Done

Jobs Done

Project Start Time:

2026-04-16 16:37


Construction Progress:

Dismantling & Inspection

Dismantling & Inspection

Installation & Sealant Application

Installation & Sealant Application

Reassembly & Final Work

Reassembly & Final Work

Jobs done

Jobs done

Project Start Time:

2026-04-16 15:07


Construction Progress:

Gangway port side bottom aluminum plate bent

Inspect and confirm deformation

Fabricate the bottom support fixture

Install support fixture and jacking system

Use a jack for straightening

Hydraulically straighten the plate

Tooling removal & final inspection

Remove tooling and inspect finish

Project Start Time:

2026-04-09 13:42


Construction Progress:

Preparation & Dismantling:Erect scaffolding, dismantle piping and air cooler end covers

Preparation & Dismantling:Erect scaffolding, dismantle piping and air cooler end covers

Inspection & Repair

Locate air cooler leaks; perform on-site weld reinforcement per Kelvion's proposal; renew leaking tubes as required.

Reinstatement & Testing

Reinstate air cooler and piping, carry out operational test

Job done

Job done

Project Start Time:

2026-04-08 16:46


Construction Progress:

Preparation & Safety Lockout

Preparation & Safety Lockout

Valve Seat Repair

Valve Seat Repair

Packing Replacement

Packing Replacement

Reassembly & Test

Reassembly & Test

Project Start Time:

2026-04-07 15:13


Construction Progress:

Preparation & Lifting Setup

Conduct welding preparation work and assemble the anchor with lifting equipment.

Anchor Lifting & Installation

Hoist the new anchor, align it with the hawsepipe, and connect it to the anchor chain inside the chain locker.

Verification & Completion Check

Check the anchor specification plate, confirm final installation and positioning, and complete the replacement work.

Job done

Job done

< 1234...15 >