Project Name:
Project Start Time:
2026-09-09 17:08
Construction Progress:
Renew floor brackets and weld stiffeners in FPT
Renew floor brackets and weld stiffeners in FPT
Reinforcement installation below deck for crosshead lube oil pump
Reinforcement installation below deck for crosshead lube oil pump
Tighten flange bolts of expansion joint at the top of scrubber
Tighten flange bolts of expansion joint at the top of scrubber
The spare main engine piston, after being placed on the piston tool platform, interferes with the pipelines and supports below
The spare main engine piston, after being placed on the piston tool platform, interferes with the pipelines and supports below
Project Start Time:
2026-09-04 11:24
Construction Progress:
Details Of Service
Details Of Service
Underwater diver plugging operation
Underwater diver plugging operation
Replacement of the valve was done by crew
Replacement of the valve was done by crew
Supply of the new valve
Supply of the new valve
Project Start Time:
2026-09-02 14:51
Construction Progress:
Details Of Service
Details Of Service
Secure crosshead & Remove worn old crosshead lower bearing
Secure crosshead & Remove worn old crosshead lower bearing
New bearing installation & Hydraulic bolt tightening work
New bearing installation & Hydraulic bolt tightening work
job done
job done
Project Name:
Project Start Time:
2026-09-01 15:47
Construction Progress:
Details Of Service
Details Of Service
Preparatory Operations
Preparatory Operations
Crack Treatment
Crack Treatment
Welding Repair & Inspection
Welding Repair & Inspection
Project Start Time:
2026-05-12 09:05
Construction Progress:
Site Preparation & Material/Structure Positioning
Site Preparation & Material/Structure Positioning
Component Pre-Fit & Temporary Fixing
Component Pre-Fit & Temporary Fixing
Formal Full Welding Operation & Post-Weld Treatment
Formal Full Welding Operation & Post-Weld Treatment
Final Inspection & Work Completion
Final Inspection & Work Completion
Project Name:
Project Start Time:
2026-05-08 08:36
Construction Progress:
Preparation & Dismantle Old Bolts
Preparation & Dismantle Old Bolts
Install New Bolts
Install New Bolts
Final Verification
Final Verification
Project Name:
Project Start Time:
2026-04-20 15:12
Construction Progress:
Preparation & Dismantling
Preparation & Dismantling
Old Bellows Removal
Old Bellows Removal
Apply Sealant
Apply Sealant
Jobs Done
Jobs Done
Project Start Time:
2026-04-16 16:37
Construction Progress:
Dismantling & Inspection
Dismantling & Inspection
Installation & Sealant Application
Installation & Sealant Application
Reassembly & Final Work
Reassembly & Final Work
Jobs done
Jobs done
Project Start Time:
2026-04-16 15:07
Construction Progress:
Gangway port side bottom aluminum plate bent
Inspect and confirm deformation
Fabricate the bottom support fixture
Install support fixture and jacking system
Use a jack for straightening
Hydraulically straighten the plate
Tooling removal & final inspection
Remove tooling and inspect finish
Project Start Time:
2026-04-09 13:42
Construction Progress:
Preparation & Dismantling:Erect scaffolding, dismantle piping and air cooler end covers
Preparation & Dismantling:Erect scaffolding, dismantle piping and air cooler end covers
Inspection & Repair
Locate air cooler leaks; perform on-site weld reinforcement per Kelvion's proposal; renew leaking tubes as required.
Reinstatement & Testing
Reinstate air cooler and piping, carry out operational test
Job done
Job done
Project Start Time:
2026-04-08 16:46
Construction Progress:
Preparation & Safety Lockout
Preparation & Safety Lockout
Valve Seat Repair
Valve Seat Repair
Packing Replacement
Packing Replacement
Reassembly & Test
Reassembly & Test
Project Name:
Project Start Time:
2026-04-07 15:13
Construction Progress:
Preparation & Lifting Setup
Conduct welding preparation work and assemble the anchor with lifting equipment.
Anchor Lifting & Installation
Hoist the new anchor, align it with the hawsepipe, and connect it to the anchor chain inside the chain locker.
Verification & Completion Check
Check the anchor specification plate, confirm final installation and positioning, and complete the replacement work.
Job done
Job done