Multiple repair works for M/V OOCL LILAC

Project Name:

Multiple repair works for M/V OOCL LILAC

Project Start Time:

2026-09-09 17:08


Decoration style:

othere

Project description:

According to the ship information provided by the owner,all required mechanical repairs and supporting formalities need to be completed, so from the SEAWAVE service team were at the port of shanghai on 23, May 2026 to carry out the repair work


Progress:

Renew floor brackets and weld stiffeners in FPT

Renew floor brackets and weld stiffeners in FPT

1.Renew floor brackets 2 Weld stiffeners

Progress:

Reinforcement installation below deck for crosshead lube oil pump

Reinforcement installation below deck for crosshead lube oil pump

Progress:

Tighten flange bolts of expansion joint at the top of scrubber

Tighten flange bolts of expansion joint at the top of scrubber

Progress:

The spare main engine piston, after being placed on the piston tool platform, interferes with the pipelines and supports below

The spare main engine piston, after being placed on the piston tool platform, interferes with the pipelines and supports below