Project Name:
Project Start Time:
2025-05-20 11:36
Construction Progress:
Fault Location & Pre-Repair Preparations
Fault Location & Pre-Repair Preparations
CYLINDER OVERHAULING & SEAL KITS REPLACEMENT
CYLINDER OVERHAULING & SEAL KITS REPLACEMENT
Reassemble pin and safety piece
Reassemble pin and safety piece
Jobs done
Jobs done
Project Name:
Project Start Time:
2025-05-11 15:43
Construction Progress:
Check and dismantle M/E lubricating oil pipe bolts and accessory
After checking the M/E lubricating oil pipe, use tools dismantle bolts and accessories.
Cut and Replaced new lubricating oil pipe
Cut and Replaced new lubricating oil pipe
Reinstall of M/E lubricating oil pipe all accessories
Reinstall of M/E lubricating oil pipe all accessories
Check and dismantle bolts and accessory
Replace and install new bolts, install all accessories.
Project Name:
Project Start Time:
2025-04-23 16:50
Construction Progress:
Check and clean the Draft marks that need to be painted.
Arrange small boats to approach the area that needs painting and clean it..
Set up scaffolding and paint it.
Set up scaffolding and paint it.
Check the draft mark after completion
Check the draft mark after completion
Job done
Job done
Project Name:
Project Start Time:
2025-04-23 10:39
Construction Progress:
Check and clean the Draft marks that need to be painted.
Arrange small boats to approach the area that needs painting and clean it..
Set up scaffolding and paint it.
Set up scaffolding and paint it.
Check the draft mark after completion
Check the draft mark after completion
Job done
Job done
Project Name:
Project Start Time:
2025-04-14 11:57
Construction Progress:
Confirmed the damaged parts
Confirmed the damaged parts
Cutting damage cell guide
Cutting damage cell guide
Fix new cell guide
Fix new cell guide
New cell guide be fitted with full welding
New cell guide be fitted with full welding
Project Name:
Project Start Time:
2025-03-28 13:25
Construction Progress:
The intermediate platform of M/E SCR and No.1/No.2 D/G SCR is shock-proof. & M/E,D/G oil change valve FCV-6 safety valve.
Cut boards as required, sand and fasten, and weld brackets.
There are multiple air leaks between M/E SCR and RTV valves and black smoke is emitted to prevent leakage.
There are multiple air leaks between M/E SCR and RTV valves and black smoke is emitted to prevent leakage.
Engine room 3 deck CO2 fire extinguisher displaced. & Bridge wing life buoy support modification.
Engine room 3 deck CO2 fire extinguisher displaced. & Bridge wing life buoy support modification.
No.11 SWBT(P & S) sounding tube lengthening and support welding.
Sand the weld area, secure and weld the bracket.
Project Name:
Project Start Time:
2025-03-14 10:12
Construction Progress:
Details Of Service
Details Of Service
Picture Report
Picture Report
Inspect and repair
Inspect and repair
Job done
Job done
Project Start Time:
2025-03-12 15:04
Construction Progress:
Location of Cracks in the Exhaust Manifold
Location of Cracks in the Exhaust Manifold
No.1 & No.2 Crack Repair(gouging/grinding /welding and grinding and PT)
No.1 & No.2 Crack Repair(gouging/grinding /welding and grinding and PT)
Collar plate
Collar plate
Exhaust boiler insulation
Exhaust boiler insulation
Project Name:
Project Start Time:
2025-03-07 11:27
Construction Progress:
Cleaning main pipes
Cleaning main pipes
Before and after the main air duct line cleaning & Before and after the branch air duct line cleaning
Before and after the main air duct line cleaning & Before and after the branch air duct line cleaning
Cleaning oil suction inlet & Remove exhaust cover and fan
Cleaning oil suction inlet & Remove exhaust cover and fan
Job done
Job done
Project Name:
Project Start Time:
2025-03-04 15:53
Construction Progress:
A, Suports of plateform crack repair
A, Suports of plateform crack repair
Scaveng manifold repair
Scaveng manifold repair
Scaveng manifold support repair
Scaveng manifold support repair
Exhaust manifold inside posision E1 & E2 & E3
Exhaust manifold inside posision E1 & E2 & E3
Project Name:
Project Start Time:
2025-02-21 11:41
Construction Progress:
Check and dismantle M/E Exhaust valve bolts and accessory
Check and dismantle M/E Exhaust valve bolts and accessory
Remove and repair and clean the exhaust valve
Remove and repair and clean the exhaust valve
Reinstall all accessories &Check and remove pipe bolts
Reinstall all accessories &Check and remove pipe bolts
Re-bolt the pipe and test the seal
Re-bolt the pipe and test the seal
Project Name:
Project Start Time:
2025-02-09 14:55
Construction Progress:
Tail shaft
Tail shaft
Rudder blade
Rudder blade
Seawater pipe
Seawater pipe
Main seawater pipe
Main seawater pipe