HATCH CYLINDER OVERHUALING FOR M/V LADY ROSE

Project Name:

HATCH CYLINDER OVERHUALING FOR M/V LADY ROSE

Project Start Time:

2025-05-20 11:36


Decoration style:

othere

Project description:

As Requested, Our Service Team Attended The Subject Vessel On 25th Apr. 2024, During Her alongside at NanGang Port of SHA China. The Reason For Attendance Was Provide Service For Hatch Cylinder Overhauling All Work Done Listed As Below:


Progress:

Fault Location & Pre-Repair Preparations

Fault Location & Pre-Repair Preparations


The leakage cylinder at No.4 deck AFT | Dismantle hose and drain hydrauilc oil | Cutting off the obstructive pipe | Remark the position on end cover | Security before remove pin | After remove safety piece and pin | Remove piston from cylinder body | Checked and inspection | Dismantle piston | New seal kit from ship side | Renewal seal kit | Reassembly pistion | Made screw stoper hole | Reassemble piston with new sealing | Reassemble pin and safety piece | Tight end cover | Connect hydraulic oil hose | Testing in good condition

Progress:

CYLINDER OVERHAULING & SEAL KITS REPLACEMENT

CYLINDER OVERHAULING & SEAL KITS REPLACEMENT

Progress:

Reassemble pin and safety piece

Reassemble pin and safety piece

Progress:

Jobs done

Jobs done