Project Name:
Project Start Time:
2025-02-09 14:55
Construction Progress:
Tail shaft
Tail shaft
Rudder blade
Rudder blade
Seawater pipe
Seawater pipe
Main seawater pipe
Main seawater pipe
Project Name:
Project Start Time:
2025-01-07 16:07
Construction Progress:
M/E until No.5 Overhauling
M/E until No.5 Overhauling
Piston cleaning & lift out,measure cyl liner, replace piston with ships spare
Piston cleaning & lift out,measure cyl liner, replace piston with ships spare
M/E No.1 unit exhaust valve replaced
M/E No.1 unit exhaust valve replaced
Job done
Job done
Project Name:
Project Start Time:
2024-12-23 13:48
Construction Progress:
E-0024 :GMS OPERATION PANEL”DAMPER TWIST”SHOWING HIGH VALUE
Add /welding stiffeners between cover and GMS sensor.
M-0039 :ME UNIT 8 CROSSHEAD FEED OIL INLET PIPE MINOR CRACK AT REINFORCEMENT WELDING AREA
According to the ship’s request replace new design hoses at unit 1.4.5.8.9
M-0043 : M/E ICER NO.1 PURGE BLOWER MOTOR BLADE
Delivery& Replace new blade and bearing.
M-0046: M/E ICER NO.2 PURGE BLOWER MOTOR BURNT
Delivery& Replace new motor
Project Name:
Project Start Time:
2024-12-20 15:44
Construction Progress:
Fabricate/Welding Foundation For No.1 A/E PS&STBD
Fabricate/Welding Foundation For No.1 A/E PS&STBD
Fabricate/Welding lifting Beam For No.1 A/E
Fabricate/Welding lifting Beam For No.1 A/E
Remove& Reassemble Air Ducts and Scaffolding above A/E No.3
Remove& Reassemble Air Ducts and Scaffolding above A/E No.3
Welding padeye & Remove insulation above A/E No.3 and supports
Welding padeye & Remove insulation above A/E No.3 and supports
Project Start Time:
2024-12-02 16:03
Construction Progress:
Tail shaft
Tail shaft
Sea chest
Sea chest
Rubber blade
Rubber blade
Spool pipe
Spool pipe
Project Name:
Project Start Time:
2024-11-30 10:10
Construction Progress:
Dismantel and clean the cooler for UNIT 1
Dismantel and clean the cooler for UNIT 1
Cooler re-assembly ,Leakage and pressure checking by ship crew for UNIT 1
Cooler re-assembly ,Leakage and pressure checking by ship crew for UNIT 1
Same work as UNIT 1 for UNIT 2
Same work as UNIT 1 for UNIT 2
Job done
Job done
Project Name:
Project Start Time:
2024-11-15 16:07
Construction Progress:
Reason Of Service
Reason Of Service
Unit No.2 OVERHAUL
Unit No.2 OVERHAUL
Unit No.3 OVERHAUL
Unit No.3 OVERHAUL
Unit No.1 OVERHAUL
Unit No.1 OVERHAUL
Project Name:
Project Start Time:
2024-11-11 09:43
Construction Progress:
Preliminary engineering assessment and preparatory work
Preliminary engineering assessment and preparatory work
Cutting and dismantling the exhaust pipe then Lifting and welding exhaust pipes
Cutting and dismantling the exhaust pipe thenLifting and welding exhaust pipes
Vessel stay at anchorage 3days for install complate.
Vessel stay at anchorage 3days for install complate.
Paiting by high tempreture paint
Paiting by high tempreture paint
Project Name:
Project Start Time:
2024-10-17 14:49
Construction Progress:
Fabricated new ladder and transport to SheKou
Fabricated new ladder and transport to SheKou
Install Upper Platform, Ladder,Wire & Lower Platform
Install Upper Platform, Ladder,Wire & Lower Platform
drop tests & Load test
drop tests & Load test
Job done
Job done
Project Name:
Project Start Time:
2024-10-11 14:02
Construction Progress:
Check and new anchor aboard.
Check and new anchor aboard.
Remove old anchor and replace new anchor.
Remove old anchor and replace new anchor.
Test new anchor.
Test new anchor.
Job done
Job done
Project Start Time:
2024-09-26 07:53
Construction Progress:
Fault Troubleshooting
Fault Troubleshooting
Thickness measurement & Spare parts info
Thickness measurement & Spare parts info
Weld cladding plate and inspect
Weld cladding plate and inspect
Grind the weld seam and perform PT inspection well.
Grind the weld seam and perform PT inspection well.
Project Start Time:
2024-09-23 16:35
Construction Progress:
Check and cut the steel plate that needs to be replaced.
Check and cut the steel plate that needs to be replaced.
Weld new steel plate and replace anchor chain.
Weld new steel plate and replace anchor chain.
paint the welding area.
paint the welding area.
Job done
Job done