Project Start Time:

2025-02-09 14:55


Construction Progress:

Tail shaft

Tail shaft

Rudder blade

Rudder blade

Seawater pipe

Seawater pipe

Main seawater pipe

Main seawater pipe

Project Start Time:

2025-01-07 16:07


Construction Progress:

M/E until No.5 Overhauling

M/E until No.5 Overhauling

Piston cleaning & lift out,measure cyl liner, replace piston with ships spare

Piston cleaning & lift out,measure cyl liner, replace piston with ships spare

M/E No.1 unit exhaust valve replaced

M/E No.1 unit exhaust valve replaced

Job done

Job done

Project Start Time:

2024-12-23 13:48


Construction Progress:

E-0024 :GMS OPERATION PANEL”DAMPER TWIST”SHOWING HIGH VALUE

Add /welding stiffeners between cover and GMS sensor.

M-0039 :ME UNIT 8 CROSSHEAD FEED OIL INLET PIPE MINOR CRACK AT REINFORCEMENT WELDING AREA

According to the ship’s request replace new design hoses at unit 1.4.5.8.9

M-0043 : M/E ICER NO.1 PURGE BLOWER MOTOR BLADE

Delivery& Replace new blade and bearing.

M-0046: M/E ICER NO.2 PURGE BLOWER MOTOR BURNT

Delivery& Replace new motor

Project Start Time:

2024-12-20 15:44


Construction Progress:

Fabricate/Welding Foundation For No.1 A/E PS&STBD

Fabricate/Welding Foundation For No.1 A/E PS&STBD

Fabricate/Welding lifting Beam For No.1 A/E

Fabricate/Welding lifting Beam For No.1 A/E

Remove& Reassemble Air Ducts and Scaffolding above A/E No.3

Remove& Reassemble Air Ducts and Scaffolding above A/E No.3

Welding padeye & Remove insulation above A/E No.3 and supports

Welding padeye & Remove insulation above A/E No.3 and supports

Project Start Time:

2024-12-02 16:03


Construction Progress:

Tail shaft

Tail shaft

Sea chest

Sea chest

Rubber blade

Rubber blade

Spool pipe

Spool pipe

Project Start Time:

2024-11-30 10:10


Construction Progress:

Dismantel and clean the cooler for UNIT 1

Dismantel and clean the cooler for UNIT 1

Cooler re-assembly ,Leakage and pressure checking by ship crew for UNIT 1

Cooler re-assembly ,Leakage and pressure checking by ship crew for UNIT 1

Same work as UNIT 1 for UNIT 2

Same work as UNIT 1 for UNIT 2

Job done

Job done

Project Start Time:

2024-11-15 16:07


Construction Progress:

Reason Of Service

Reason Of Service

Unit No.2 OVERHAUL

Unit No.2 OVERHAUL

Unit No.3 OVERHAUL

Unit No.3 OVERHAUL

Unit No.1 OVERHAUL

Unit No.1 OVERHAUL

Project Start Time:

2024-11-11 09:43


Construction Progress:

Preliminary engineering assessment and preparatory work

Preliminary engineering assessment and preparatory work

Cutting and dismantling the exhaust pipe then Lifting and welding exhaust pipes

Cutting and dismantling the exhaust pipe thenLifting and welding exhaust pipes

Vessel stay at anchorage 3days for install complate.

Vessel stay at anchorage 3days for install complate.

Paiting by high tempreture paint

Paiting by high tempreture paint

Project Start Time:

2024-10-17 14:49


Construction Progress:

Fabricated new ladder and transport to SheKou

Fabricated new ladder and transport to SheKou

Install Upper Platform, Ladder,Wire & Lower Platform

Install Upper Platform, Ladder,Wire & Lower Platform

drop tests & Load test

drop tests & Load test

Job done

Job done

Project Start Time:

2024-10-11 14:02


Construction Progress:

Check and new anchor aboard.

Check and new anchor aboard.

Remove old anchor and replace new anchor.

Remove old anchor and replace new anchor.

Test new anchor.

Test new anchor.

Job done

Job done

Project Start Time:

2024-09-26 07:53


Construction Progress:

Fault Troubleshooting

Fault Troubleshooting

Thickness measurement & Spare parts info

Thickness measurement & Spare parts info

Weld cladding plate and inspect

Weld cladding plate and inspect

Grind the weld seam and perform PT inspection well.

Grind the weld seam and perform PT inspection well.

Project Start Time:

2024-09-23 16:35


Construction Progress:

Check and cut the steel plate that needs to be replaced.

Check and cut the steel plate that needs to be replaced.

Weld new steel plate and replace anchor chain.

Weld new steel plate and replace anchor chain.

paint the welding area.

paint the welding area.

Job done

Job done