M/E Inspection for M/V KOTA LUKIS

Project Name:

M/E Inspection for M/V KOTA LUKIS

Project Start Time:

2025-01-07 16:07


Decoration style:

M/E Overhaul

Project description:

M/E NO1&No5 Need Carry Out Inspection During Vessel arrives Yantian port.


Progress:

M/E until No.5 Overhauling

M/E until No.5 Overhauling

Dismantle parts necessary /Take out the cylinder cover/Piston cleaning & lift out,measure cyl liner, replace piston with ships spare /Piston cleaning /lift out piston Cylinder liner measurements & recorded /New piston&piston ring reinstalled /Cyl cover& attachments reinstalled /M/E No.1 unit exhaust valve replaced /Cyl cover be take out Liner cleaning /Exhaust valve replacement Cyl cover&attchments reinstalled

Progress:

Piston cleaning & lift out,measure cyl liner, replace piston with ships spare

Piston cleaning & lift out,measure cyl liner, replace piston with ships spare

Progress:

M/E No.1 unit exhaust valve replaced

M/E No.1 unit exhaust valve replaced

Progress:

Job done

Job done