Project Name:
M/E Inspection for M/V KOTA LUKIS
Project Start Time:
2025-01-07 16:07
Decoration style:
M/E Overhaul
Project description:
M/E NO1&No5 Need Carry Out Inspection During Vessel arrives Yantian port.
Progress:
M/E until No.5 Overhauling








Dismantle parts necessary /Take out the cylinder cover/Piston cleaning & lift out,measure cyl liner, replace piston with ships spare /Piston cleaning /lift out piston Cylinder liner measurements & recorded /New piston&piston ring reinstalled /Cyl cover& attachments reinstalled /M/E No.1 unit exhaust valve replaced /Cyl cover be take out Liner cleaning /Exhaust valve replacement Cyl cover&attchments reinstalled
Progress:
Piston cleaning & lift out,measure cyl liner, replace piston with ships spare








Progress:
M/E No.1 unit exhaust valve replaced




Progress:
Job done