Removal and Installation of Air Cooler for M/V CMA CGM NOTRE DAME

Project Name:

Removal and Installation of Air Cooler for M/V CMA CGM NOTRE DAME

Project Start Time:

2026-04-09 13:42


Decoration style:

othere

Project description:

Per owner's advice regarding air cooler replacement, the SEAWAVE service team attended Yangzijiang Mitsui Shipyard on 16 Mar 2026 to carry out the repairs.


Progress:

Preparation & Dismantling:Erect scaffolding, dismantle piping and air cooler end covers

Preparation & Dismantling:Erect scaffolding, dismantle piping and air cooler end covers

Progress:

Inspection & Repair

Locate air cooler leaks; perform on-site weld reinforcement per Kelvion's proposal; renew leaking tubes as required.

Progress:

Reinstatement & Testing

Reinstate air cooler and piping, carry out operational test

Progress:

Job done

Job done