Project Name:
Cell guides repair work for M/V ZIM FALCON
Project Start Time:
2024-09-10 15:18
Decoration style:
othere
Project description:
According to the ship information provided by the owner,the cell guides needs to be repair, so from the SEASAVE service team were at the port of shanghai on 31 ,Aug 2024 to carry out the repair work
Progress:
Check and set up scaffolding, cut through broken cell guides.
1.Check old damaged cell guides(T15*L150*L150*2.25)in all 4pcs & enter guide(Bay22 Row06&08 FWD).
2.Scaffolding, cutting of old cell guides(T15*L150*L150*2.25)in all 4pcs & enter guide(Bay22 Row06&08 FWD).






Progress:
Fixing, welding and grinding of new cell guides and enter guide
Fixing, welding and grinding of new cell guides(T15*L150*L150*2.25)in all 4pcs & enter guide(Bay22 Row06&08 FWD).




Progress:
New cell guides paint.


Progress:
Job done