Project Name:
Modification of ER Ventilation Tower for M/V PELAGICA
Project Start Time:
2024-08-01 15:54
Decoration style:
othere
Project description:
According to the requirements of the owner, our service team Modification of ER Ventilation Tower of the "PELAGICA" on July 31, 2024, at LongWu Port dock.
Progress:
Pre-construction inspection & Measuring and scribing the cutting width
Pre-construction inspection & Measuring and scribing the cutting width


Progress:
cutting after Reinforced welded lifting eye
cutting after Reinforced welded lifting eye










Progress:
Weld and polish the ventilation tower
Weld and polish the ventilation tower



Progress:
Check the whole after finished
Check the whole after finished



Service Hotline
Mailbox:leo@seawave-engineering.com(Domestic)
Add:Building 3, No. 3238 Huhang Highway, FengXian District,ShangHai ,China
License