Scrubber smoke pipe repair & Additional Installation cable trunk safety edge for X PREES FEEDERS

Project Name:

Scrubber smoke pipe repair & Additional Installation cable trunk safety edge for X PREES FEEDERS

Project Start Time:

2024-08-13 15:19


Decoration style:

othere

Project description:

On August 9, 2024, six SEASAVE technicians repaired the leaking scrubber smoke pipe and added a safety edge to the cable at Shanghai Port, following the ship owner’s report.


Progress:

Scrubber smoke pipe repair

Scrubber smoke pipe repair

Check and erection of scaffolding, grind the leak area to remove paint, then weld and polish.

Progress:

weld and polish

weld and polish

Progress:

Additional Installation cable trunk safety edge

Additional Installation cable trunk safety edge

Check and tap the covered cable trunk safety edge

Progress:

Making a new safety edge ,put up a fireproof cloth and weld the cable trunk safety edge.

Making a new safety edge ,put up a fireproof cloth and weld the cable trunk safety edge.