Project Start Time:

2024-03-22 19:32


Construction Progress:

Scubber tower repair

Scubber tower repair

Scaffolding is set up & Polish the leakage places & Welding leakage seams & PT checking after welding

Scaffolding is set up & Polish the leakage places & Welding leakage seams & PT checking after welding

Butterfly valve repair

Butterfly valve repair

Job done

Job done

Project Start Time:

2024-03-18 17:21


Construction Progress:

Remove the M/E No.1 Pre-combustion chamber

Remove the M/E No.1 Pre-combustion chamber

Disassembly pre-chamber,cleaning,polish and replaced spare

Disassembly pre-chamber,cleaning,polish and replaced spare

Cleaning pre-combustion chamber & Re-install & Test sealing

Cleaning pre-combustion chamber & Re-install & Test sealing

Job done

Job done

Project Start Time:

2024-03-14 14:34


Construction Progress:

Enterance guide repair

Enterance guide repair

Hatch cover pillar repair

Hatch cover pillar repair

Hatch cover repair BAY39 STBD AFT Cuttirg off the damaged area plates

Hatch cover repair BA 39 STBD AFT Cuttirg off the damaged area plates

Watertight ventilation cover .etc

Watertight ventilation cover .etc

Project Start Time:

2024-03-12 14:59


Construction Progress:

Carried out Stbd anchor & chains inspection

Carried out Stbd anchor & chains inspection

Transfer new anchor on barge

Transfer new anchor on barge

Installed port side anchor on position & tested with shipside satisfaction

Installed port side anchor on position & tested with shipside satisfaction

Job done

Job done

Project Start Time:

2024-03-09 17:32


Construction Progress:

Inlet crack repair

Inlet crack repair

Welding the plates & PT checking after welding

Welding the plates & PT checking after welding

Replace pipe

Replace pipe

Job done

Job done

Project Start Time:

2024-03-04 13:41


Construction Progress:

Background

Background

Preparation

Preparation

inlet crack repair

inlet crack repair

Job done

Job done

Project Start Time:

2024-02-29 10:36


Construction Progress:

Replace the spring and scraper in the stuffing box section of unit No.1 and No.3

Replace the spring and scraper in the stuffing box section of unit No.1 and No.3

Install stuffing box

Install stuffing box

No.6 unit Replace the main bearing bottom

No.6 unit Replace the main bearing bottom

Job done

Job done

Project Start Time:

2024-02-22 16:14


Construction Progress:

Reshaping On Site and Install The New Steps

Reshaping On Site and Install The New Steps

Cut Off Damaged Back Reinforcement Flat Type Aluminium Plate

Cut Off Damaged Back Reinforcement Flat Type Aluminium Plate

Load Test At Port Shekou

Load Test At Port Shekou

job done

job done

Project Start Time:

2024-02-13 10:59


Construction Progress:

Remove the M/E old tracing pipe

Remove the M/E old tracing pipe

Install and connect the new tracing pipe

Install and connect the new tracing pipe

Steam test

Steam test

Job done

Job done

Project Start Time:

2024-02-10 21:25


Construction Progress:

Original cell guide crown plate

Original cell guide crown plate

under replacement

under replacement

finish replacing

finish replacing

Job done

Job done

Project Start Time:

2024-02-04 20:37


Construction Progress:

Dismantle stuffing box

Dismantle stuffing box

Replace scraper rings

Replace scraper rings

New scraper rings vs. Bad scraper rings

New scraper rings vs. Bad scraper rings

Job done

Job done

Project Start Time:

2024-02-04 12:18


Construction Progress:

Dismantle oil pipes & seat bolts

Dismantle oil pipes & seat bolts

Main pump disassembled and located oil leak from seals

Main pump disassembled and located oil leak from seals

Replace with new seals

Replace with new seals

Job done

Job done