Pilot ladder modification work for M/V YM TRUST

Project Name:

Pilot ladder modification work for M/V YM TRUST

Project Start Time:

2024-06-03 11:32


Decoration style:

othere

Project description:

Received the notice from Owner of the vessel that there pilot ladder both side needed modification as drawing . Service team was arranged when vessel calling Yangshan terminal


Progress:

Modification drawing of request

Modification drawing of request

Progress:

To take measurement 4pcs angle bars for seats welded . And brackets welded,

To take measurement 4pcs angle bars for seats welded . And brackets welded,

Progress:

Flat bars reinforcement inside

Flat bars reinforcement inside

Progress:

Job done

Checked with shipside after welding Round bars ,Top plats & Pad eyes .