Tracing pipe replace for M/V MSC CELESTINO MARESCA

Project Name:

Tracing pipe replace for M/V MSC CELESTINO MARESCA

Project Start Time:

2024-05-21 13:54


Decoration style:

othere

Project description:

At ship's request, the SEAWAVE service team conducted the service(Tracing pipe replace) on board MSC CELESTINO MARESCA in Shanghai Port on May 17, 2024.


Progress:

Close the steam valve and remove the trace pipe

After close steam valve, check and dismantle insulation and old the tracing pipe.

Progress:

Install and test the new tracing pipe

Make a new tracing pipe Install the new tracing pipe and use special tools to fix it ,open steam valve to test ,discover no leak.

Progress:

Reinstall the new insulation

Reinstall the new insulation

Progress:

Job done

Job done