Gas detector pipe modification for M/V CMA CGM CONCORDE

Project Name:

Gas detector pipe modification for M/V CMA CGM CONCORDE

Project Start Time:

2024-05-17 13:52


Decoration style:

othere

Project description:

According to the ship information provided by the owner,the gas detector pipe need modification , so a total of four people from the SEASAVE service team were at the port of shanghai on 29th,Apr 2024 to carry out the hot work.


Progress:

Check, put up fire cloth and cut holes

Check, put up fire cloth and cut holes

Progress:

Make and weld new heavy plate

Make and weld new heavy plate

Progress:

Install pipe fittings and pipe layout

Install pipe fittings and lay, bind&fix new stainless pipe line and PT

Progress:

Job done

Job done