Repair service for M/V MAERSK CINCINNATI

Project Name:

Repair service for M/V MAERSK CINCINNATI

Project Start Time:

2024-05-16 14:32


Decoration style:

othere

Project description:

At ship's request, the SEAWAVE service team conducted the service on board MAERSK CINCINNATI in Nansha Port on 14th.May.2024.


Progress:

EGR blower drain pipe repaired

After check the blower drain pipe and repaired the damaged location by welding and polished.

Progress:

Cylinder cooling water outlet pipe repaired

After inspection the cooling water outlet pipe , repaired the damaged location by welding.

Progress:

Maintenance of the M/E turning gear

Disassemble the turning gear and replaced gearwheel to repaired , then the turning gear is reassembled and the gear rotation test is carried out.

Progress:

Job done

Job done