Project Name:
M/V CMA CGM CONCORDE:Lash bridge pillar repair
Project Start Time:
2023-03-24 11:10
Decoration style:
othere
Project description:
As Requested, Our Service Team Attended The Subject Vessel On 22th Mar 2023, During Her alongside at YangShan Port SHA China. The Reason For Attendance Was Provide Service For Lash Bridge Pillar Repair.
Progress:
pillar repair bay34
Damaged pillar
Rectify damaged pillar
Rectify damaged pillar
After continue welding
Grinding smooth welding seam
After repair






Progress:
pillar repair bay74
Damaged pillar
Rectify damaged pillar
Rectify damaged pillar
After continue welding
Grinding smooth welding seam
After repair






Progress:
pillar repair bay30
Damaged pillar
Rectify damaged pillar
After continue welding
After continue welding
After repair





Progress:
Job done