Project Name:
M/V CMA-CGM-SORBONNE:M/E Main Exhaust pipe insulation plates fixing
Project Start Time:
2024-01-24 09:15
Decoration style:
othere
Project description:
As Requested, Our Service Team Attended The Subject Vessel On 10th Dec 2023, During Her Alongside At Meishan Port Ningbo China. The Reason For Attendance Was Provide Service For M/E Main Exhaust Pipe Insulation Plates Fixing.
Progress:
Setting Erecting scaffolding






Progress:
Check/inspection lose rivets area and Fixed insulation plates with stainless steel rivets









The transverse support is fixed with rivets
Progress:
Fixed insulation plates with stainless steel rivets on second area
Remove scaffolding and shifting second area





Progress:
Job done
Remove scaffolding
After fixed with stainless steel rivets