Claim issues for CMA CGM GREENLAND

Project Name:

Claim issues for CMA CGM GREENLAND

Project Start Time:

2023-12-08 10:31


Decoration style:

othere

Project description:

Claim issues


Progress:

PIPE BRACKET FOR LUB OUILL PIPING CYL 7

Drill 6mm hole and add install new bracket.

M-0469 PIPE BRACKET FOR LUB OUILL PIPING CYL 7

Drill 6mm hole and add install new bracket.    

Drill 6mm hole on liner    After install bracket

 

Progress:

M-0468 LOCKING DEVICE CRANKCASE DOOR10

Install new locking device and full welding

Locking device missing 1pc
After position and full welding new locking device

Progress:

M-0380 M/E SCAV AIR COOLER BRACKETS REPLACEMENT

Replace No.1,No2,No.3 water mist catcher for updated brackets with new gasket

New type supports and new gaskets were delivery on board at QingDao
Dismantled FWD &AFT cover and remove old gaskets
Install new type support
After replace new type support
After install new gasket and close cover
After closed cover plate No.1
Replace new type support No.2
After change new gasket
After close cover FWD &AFT
After dismantled cover plate No.3
Cleaning cover plate
Replace new type support
After closed AFT cover plate
After closed FWD cover plate No.3
The old supports were collected and left on board

Progress:

M-0490 TOP BRACING 4 CONNET BE ADJUSTED

Adjust top bracing 4 and show to 2/E

Close the pressure regulating valve and release oil pressure
Loose adjustable locknut adjust outside indicator color column and show it to 2/E.