Project Name:
Replace the crosshead slider for M/V OOCL PORTUGAL
Project Start Time:
2026-03-19 14:23
Decoration style:
othere
Project description:
At ship's request, the ours service team conducted the service on board OOCL PORTUGAL in Shanghai Port on 2026.3.14.
Progress:
Check and dismantle cross head bolts and accessory
1.1The new slider is lifted and transported to the M/E platform.
1.2Hydraulic tools are used to disassemble accessories such as the cross head guide plate, slider guard plate, and stopper.






Progress:
Old slider lifted down M/E platform


Progress:
Install new slider and test
1. Inspection of new crosshead slipper and clean.
2.Use a hand chain hoist to lift the new crosshead slipper and align it with the installation position, then use hydraulic tools to install accessories such as stoppers, locating pins, and guard plates.








Progress:
Job done