Project Name:
M/E High pressure oil pump platform replacement for MSC CHINA
Project Start Time:
2024-06-09 09:52
Decoration style:
othere
Project description:
At ship's request, the SEAWAVE service team conducted the service on board MSC CHINA in Shanghai Port on 24thMay,2024 to 26thMay,2024.
Progress:
Close valves, remove platforms, railings, insulation and pipes (oil and tracing pipes).








Disassemble the railings and platformsDisassemble the pipes(oil pipe & tracing pipe)Remove the platformFinished the dismantle
Progress:
Replace the platform and re-install the oil pipe and insulation, and weld the platform joints.






The new platformInstall the new platform and bolt tightenRe-install oil pipe and insulationRepair welding
Progress:
Starting the M/E to run the pressure test, check that the pressure test is normal, stop the M/E, and re-install the railings, tracing pipes and insulation.


Progress:
Job done
Finally, the steam valve is opened for steam test and no leakage is checked.