Project Name:
Anchor Replacement for M/V BYD JINAN
Project Start Time:
2026-04-07 15:13
Decoration style:
othere
Project description:
Per owner's advice regarding anchor replacement, the SEAWAVE service team attended Shanghai Port on 16 Mar 2026 to carry out the repairs.
Progress:
Preparation & Lifting Setup
Conduct welding preparation work and assemble the anchor with lifting equipment.


Progress:
Anchor Lifting & Installation
Hoist the new anchor, align it with the hawsepipe, and connect it to the anchor chain inside the chain locker.


Progress:
Verification & Completion Check
Check the anchor specification plate, confirm final installation and positioning, and complete the replacement work.



Progress:
Job done
Job done