Multiple repairs for M/V BH POWER

Project Name:

Multiple repairs for M/V BH POWER

Project Start Time:

2025-07-18 15:57


Decoration style:

othere

Project description:

According to the ship information provided by the owner,The ship needs repair, so from the SEASAVE service team were at the port of quanzhou on 2025.7.11 to carry out the repair work.


Progress:

D004 The outboard drainage pipe was removed repair.

After inspecting and taking safety measures, hang the hanging cage outside the ship, cut off the protruding pipes and grind them


Progress:

D005 Safety latch for the four-compartment ballast tank repair.

After inspection, remove the attachments, remeasure the dimensions as required, cut, expand the holes and reinstall.

Progress:

D006 Hatch cover locking screws change.

Grind the threads, clean and test the ground threads, and install the bolts.

Progress:

M030 The base bolts of the self-cleaning filter for the M/E hydraulic oil are damaged.

M030 The base bolts of the self-cleaning filter for the M/E hydraulic oil are damaged.

1 Inspect and remove the bolts and accessories.
2.Use professional tools to make holes according to the bolt size, clean them and then grind them.
3.After lubrication, install the new bolts on the base of the filter.>
4.Reinstall the M/E hydraulic oil self-cleaning filter.