Repair of Main Engine Exhaust Manifold Crack for M/V ELEONORA MAERSK

Project Name:

Repair of Main Engine Exhaust Manifold Crack for M/V ELEONORA MAERSK

Project Start Time:

2025-06-19 13:24


Decoration style:

othere

Project description:

As Requested, Our personnel dispatched engineers to investigate the ship, and observed cracks in the exhaust manifold.Repairs carried out at Youlian Shipyard on 19 May 2025


Progress:

Details Of Service

Details Of Service

1,Our personnel dispatched engineers to investigate the ship, and observed cracks in the exhaust manifold.
2,The job carry out during vessel docking Yiu Lian Shipyard and repair report as below.
3,Engineer was checked and gouging /grinding /welding with G577 Elc rod / and aft 24hours PT test that was all good condition.

AFT PS crack position No.2 | AFT PS crack position.No.1 | AFT STBD crack position No.1 | AFT STBD crack position.No.2 | AFT STBD crack position.No.3 | AFT STBD crack position.No.4 | After remove insulation at No.1 PS AFT | After remove insulation at No.1 PS FWD | After remove insulation at No.1 STBD AFT | After remove insulation at No.1 STBD FWD | After welding/grinding and PT | collar plate and stiffeners PT | Crack No.1 STBD AFT(3)crack welding/PT | Crack No.1 STBD FWD After welding/grinding/PT | Crack NO.2 STDB AFT | crack welding NO.2 STDB AFT(2) | Crack/gouging/grinding /welded /and aft 24 hours PT test | Exhaust Manifold support cracks on both side | FWD PS crack position.No.1 | FWD PS crack position.No.2 | FWD STBD crack position.No.1 | FWD STBD crack position.No.2 | FWD STBD crack position.No.3 | FWD STBD crack position.No.4 | Install steel sheet and insulation | Install& welding collar plate and stiffeners | Install& welding collar plate and stiffeners No.1 STBD AFT | Install& welding collar plate No.1 PS AFT | Install& welding collar plate No.1 PS FWD | Install& welding collar plate No.1 STBD FWD | Install& welding collar plate No.2 PS AFT | Install& welding collar plate No.2 PS FWD | Install& welding collar plate NO.2 STBD FWD | Install& welding stiffeners | Install& welding stiffeners and PT | Install& welding stiffeners No.1 STBD FWD | Manifold FWD &AFT both side crack area | Manifold No.1 STBD FWD | New collar plates provided Material | No.1 STBD AFT Support crack(2) gouging/welding/PT | No.1 STBD FWD support crack(4) gouging/welding/PT | NO.2 STBD FWD(3) Before repair | NO.2 STBD FWD(4) Before repair | NO.2 STBD FWD(4)welding | PT test for manifold NO.2 STDB FWD | PT test for No.1 PS FWD | PT test for NO.2 STBD AFT | Q460B : 550x500xT16mmx8PCS | Remove insulation | support crack gouging/welding NO.2 STDB FWD | Support crack(6) welding NO.2 STBD AFT | welding stiffener |

Progress:

Manifold NO.1

Manifold NO.1

Progress:

Manifold NO.2

Manifold NO.2

Progress:

Exhaust manifold inside NO1-NO12

Exhaust manifold inside NO1-NO12