Scupper to be unclogged for M/V CMA CGM MONTMARTRE

Project Name:

Scupper to be unclogged for M/V CMA CGM MONTMARTRE

Project Start Time:

2024-06-03 16:45


Decoration style:

othere

Project description:

According to the ship information provided by the owner,The MONTMARTRE's scupper pipe is clogged and needs to be unblocked from tank inside and outside of shiphull. so our team were at the port of Qingdao/SHA on 15th.May.2024 to carry out the hot work.


Progress:

Check and cutting clogged scupper

Identify the blocked area of the pipe and cut it

Progress:

Cleaning pipe & Aft renewnal

Cleaning pipe & Aft renewnal

Progress:

Take out clogged drill and testing

Take out clogged drill and testing

Progress:

Job done

Job done