Project Name:
Samsun A/E No. 3 Overhaul
Project Start Time:
2023-11-14 16:35
Decoration style:
A/E Overhaul
Project description:
A/E NO3 Need Carry Out Overhaul During Vessel In Dry Dock At YouLian Shipyard
Progress:
Preparation for overhaul
Deflection measurment before onverhaul
Dismantle pipe and parts necessary
NO.3 Cylinder Cover bolt remove
Injection

Progress:
Disassembly, inspection and maintenance of related accessories
Open the cyl cover
Air starter dismantled
Measurment connecting rod
Diassembly connecting rod
Liner measurment
Liner cleaned and measurment
Liner cleaned
Connecting rod measurment and recorder
Pistion head measurment
Conecting rod pin measurment
Cyl cover cleaning
New parts need renewal
Vavle seats renewed
Vavle seat leakge check
Cooling jacket cleaning
Cooling jacket cleaned
Cyl cover cleaned
Aft lapping cyl cover overhaul complate
Cyl cover leakage testing by 6bar
Main bearing inspection
Trust washer inspection
Crank pin measurment and recorder
Rocap disassemble /inspection
Conecting rod measurment wiht bearing and without bearing
Pistion unit cleaned and piston ring renewal nesscery
Re-assembly piston unit
Re-assembly
Timing adjustment
Crank case cleaning
















































Progress:
Aftre-assembly complate shall running test
Crank case cleaning Aftre-assembly complate shall running test
Aft load test open the crank casing to check
Loading testing to 200kw





Progress:
Job Done